LRC Boiler AHU Replacement
Project Schedule
| Programming Complete | Design and DSA Approval | Construction Completion (Est.) | FFE and Move-In (Est.) |
|---|---|---|---|
| 05-27-2025 | 05-27-2025 | 04-07-2026 | N/A |
Project Insights
Replacement of chillers, boilers, and air handling units at the Building R—Learning Resource Center. Perform lockout/tagout of the building heating hot water (HHW) and chilled water (CHW) systems.
Upcoming Milestones:
- Notice to proceed issued: November 10, 2025
- Construction kickoff: January 5, 2026
- Tentative functional testing scheduled for February 2, 2026
- Functional testing began February 17, 2026 and is currently in progress
- Change Order routed March 25, 2026 for Humidity Sensors for AHU 1 and 2.
Project Features
- Boiler and Air Handling Unit (AHU) replacement
- Perform lockout/tagout of HHW and CHW systems
- Install specified equipment, including all required rigging
- Install new insulated piping in accordance with project plans
- Provide and commission BMS controls and devices for:
- New heating hot water system
- Two air handling units
- Furnish and install all required sensors, valves, actuators, and control enclosures
- Complete all electrical connections for new equipment
Project Map

1313 Park Blvd, San Diego, CA 92101
Project News & Information
Additional resources, articles, and links related to this project will appear here when available. For comprehensive information about Measure HH and all ongoing projects, please explore the Measure HH website.
Project Teams
| General Contractor | ACCO Engineering |
| Architect | N/A |
| Structural Engineer | N/A |
| Civil Engineer | N/A |
| Mech./ Elect. Engineer | N/A |
| Executive Const. Manager | Steve Evanco |