San Diego City College Soccer Turf Replacement
Project Schedule
| Programming Complete | Design and DSA Approval | Construction Completion (Est.) | FFE and Move-In (Est.) |
|---|---|---|---|
| 10-01-2025 | N/A | 01-16-2026 | N/A |
Project Progress Update
Full turf replacement of the existing San Diego City College Soccer field.
Upcoming Milestones:
- Submitted board action: October, 30 2025
- Preconstruction Kickoff: November 20, 2025
- Construction Commencement: November 24, 2025
- Punch walk #2 scheduled January 13, 2026
- Acceptance walk scheduled for January 26, 2026
Project Description
Full turf replacement:
- Remove existing turf and vegetation
- Prepare and grade approximately 75,000 square feet of soil
- Install new irrigation system, including:
- Valves
- Rotors
- Main line
- Install new sod
- Complete soccer field striping
- Provide maintenance and turf establishment period
Phase Work includes:
- Turf removal
- Subgrade rework
- Irrigation system upgrades
- Final turf installation and striping
Project Map

1313 Park Blvd, San Diego, CA 92101
Project News & Information
Additional resources, articles, and links related to this project will appear here when available. For comprehensive information about Measure HH and all ongoing projects, please explore the Measure HH website.
Project Teams
| General Contractor | Kya Group |
| Architect | Spurlock Landscape Architect |
| Structural Engineer | N/A |
| Civil Engineer | N/A |
| Mech./ Elect. Engineer | N/A |
| Executive Const. Manager | Steve Evanco |
Last updated: March 31, 2026